Enviroparks Update - July 2020

As many of you are aware the Enviroparks project required a planning amendment to increase the height of the exhaust stack (due to a butterfly meadow in the vicinity of the site).

Because the planning regime is Welsh, the amendment has to go through a public consultation and this has now, at long last, commenced. The planning spans two planning districts which had made things more complex but the consultation started at the end of June.

This has been the largest stumbling block to the project as the potential tenants of the site would only sign up to terms with the planning in place.

We are expecting a more in-depth update from the Enviroparks team in the very near future.